September ’21 Construction Update

September '21 Construction Update

 


 
Last month saw great progress on site and momentum building with our first concrete slab pour to Basement Level 2, scheduled for 23rd September. With the announcement made by the Government in regards to a two-week shut-down period industry wide, this date has now unfortunately been pushed out.

The team is continuing work in the background, focusing on finalising design elements such as apartment joinery, balustrade details, and fa├žade systems. All of these aspects of the project are now well progressed with shop drawings underway. The team is well positioned to commence once the restrictions are lifted in order to mitigate any time lost on site.