November ’21 Construction Update

November '21 Construction Update

 


 
As the year starts to draw to an end, so too has piling reached completion at Walmer with the disassembly of the piling rig on 15th November. The first suspended basement slab was finished on 17th November and the ground floor slab is expected to be poured before Christmas.

The remainder of the strip footings and pile caps to the southern end of the site are to be installed by the end of the month. Manufacturing of the external curtain wall fa├žade system is well underway and is expected to be ready in the New Year.