March ’22 Construction Update

March '22 Construction Update

 


 
Walmer has sprung up from the ground and is rising rapidly. It is now very visible from the street with teams of builders undertaking various tasks to enable the project to stay on track.

Current Status
• Level 2 concrete pouring will be complete this week
• Level 3 formwork has commenced
• Stripping of Lower Ground formwork material is in progress
• Basement services are continuing to be installed

 

Level Two with concrete pour nearing completion

 

Lower Ground car park