February ’22 Construction Update

February '22 Construction Update

 


 
The holiday season seems a distant memory now as 2022 nears the start of its third month.

The Construction Team has been back on site working hard since mid-January and has made tremendous progress with the build.
 
Current Status
• Basement: Removal of formworks has commenced
• Ground Floor: Concrete pouring is complete
• Level 1: First concrete pour is complete
• Level 2: Formwork to commence next week
• Level 3: Formwork to be completed by the end of February

 

The beginnings of the Ground Floor feature wall.

Concrete pour on the Ground Floor

The Ground Floor last pour on Victoria Street – the residents’ dining room and porte cochere