The final month of 2021 has been an intensive month on-site with the changes plain to see. This month we completed a number of milestones.
 
Current Status
• Basement 2: Remaining sections of the slab were poured
• Basement 1: 75% completed
• Lower Ground: 50% completed
• Ground: 20% completed with the base of the pool poured
• Level 1: Precast columns installed on the underside of the north section

The site will wind down now for the holiday season but will be back to continue works on-site from 11 January 2022!

 

The construction of the pool deck commenced.

The gantry erected along Victoria Street. The gantry is built to protect pedestrians whilst walking in front of the construction site.